0151 222 3411

Handover – Academy @ Worden, New Kitchen

Having being appointed by the Academy @ Worden to undertake a full kitchen refurbishment during the Summer period, Senate also completed additional works in the 6 weeks meeting the School’s high expectations.

Senate Group provided new staff and conference room facilities as well as refurbishment of the adjacent hall. These were additional works to the original contract, all still completed within the tight timescales given. 

Our works included structural alterations and adaptations to refurbished areas, and upgrading mechanical and electrical installations through our in-house building services team.

Senate managed the kitchen installation and fit-out through the School’s nominated subcontractor

The project was completed to programme including all additional works incorporated into the contract to the high expectations of the school.

Congratulations to Dave Kilgannon and his site team in receiving fantastic KPI’s from a satisfied client!