SITE PROGRESS – Schools Ongoing

Our site teams continue to be busy over the next couple of months working on a number of schools in the region.

We are currently on-site at Formby High School undertaking the re-clad of an existing block and re-roof.  Progress is going well, the roof has now been stripped with VCL laid ready for new insulation and felt.  Alongside this the South Elevation windows have been stripped and new curtain walling has commenced.

At Bridgewater High School we are undertaking another external upgrades package. Cladding is 80% complete on this project with windows not far behind. We will be undertaking the entrance canopy during half term and have completed upgrades to the hall and dining room ceilings and lighting.